Automatic wellbore activity schedule adjustment method and system
Abstract:
A method for scheduling wellbore construction activities includes entering a well plan into a computer. The well plan includes estimated start and stop times for a plurality of activities in a predetermined sequence. Progress of selected ones of the plurality of activities is measured during their performance. In the computer, expected ending time of at least one of the plurality of activities is recalculated based on progress thereof during that activity. In the computer, expected start and stop times are recalculated for each activity subsequent to the activity in progress based on the recalculated expected ending time. The recalculated start and stop times for each subsequent activity are displayed.